Project Management Glossary

A comprehensive reference of project management terms, acronyms, and definitions used throughout the project lifecycle.


Quick Navigation

A B C D E F G H I J K L M N O P Q R S T U V W X Y Z

A

Term Definition
Acceptance Criteria The conditions that must be met for a deliverable to be accepted by stakeholders.
Agile An iterative approach to project management that emphasises flexibility, collaboration, and delivering value incrementally.
Assumption A factor considered to be true for planning purposes, which may carry risk if incorrect.
Authority The right to make decisions, assign resources, and direct work within defined boundaries.

B

Term Definition
BAC (Budget at Completion) The total planned budget for the project.
Backlog A prioritised list of work items (features, requirements, fixes) waiting to be addressed.
Baseline The approved version of scope, schedule, or cost against which performance is measured.
Benefit A measurable improvement resulting from project outcomes.
Business Case A document justifying the project investment based on expected benefits and costs.

C

Term Definition
Change Control A process to manage changes to project scope, schedule, or cost in a controlled manner.
Change Request A formal proposal to modify a project baseline.
Charter A document that formally authorises a project and grants the PM authority to proceed.
Constraint A limiting factor that affects project execution (time, cost, scope, quality, resources).
Contingency Time or budget reserve held to address identified risks.
Critical Path The longest sequence of dependent tasks that determines the minimum project duration.
CPI (Cost Performance Index) A measure of cost efficiency: EV ÷ AC. Values >1 indicate under budget.

D

Term Definition
Deliverable A tangible or intangible output produced by the project.
Dependency A relationship where one task relies on another to start or finish.
Duration The total time required to complete a task or project.

E

Term Definition
EAC (Estimate at Completion) The expected total cost of the project when complete.
Effort The amount of work (person-hours/days) required to complete a task.
Escalation Raising an issue or decision to a higher authority when it cannot be resolved at the current level.
ETC (Estimate to Complete) The expected cost to finish the remaining work.
EV (Earned Value) The value of work actually completed, measured against the budget.
Exception A situation where tolerances are forecast to be exceeded.

F

Term Definition
Feasibility Study An assessment of whether a project is viable and worthwhile.
Float (Slack) The amount of time a task can be delayed without affecting the project end date.
Functional Requirements Specifications of what a system must do.

G

Term Definition
Gantt Chart A bar chart showing project tasks against time.
Gate Review A checkpoint where a decision is made whether to proceed to the next phase.
Governance The framework of authority, accountability, and decision-making for a project.

H

Term Definition
Highlight Report A regular status report summarising project progress for governance bodies.
Hybrid An approach combining elements of different methodologies (e.g., Agile and Waterfall).

I

Term Definition
Impact The effect or consequence of a risk or issue if it occurs.
Issue A current problem that is affecting the project and requires resolution.
Iteration A time-boxed development cycle in Agile methodologies (also called Sprint).

J

Term Definition
Just-in-Time (JIT) An approach where resources or decisions are provided exactly when needed.

K

Term Definition
Kanban A visual workflow management method using boards and cards to track work.
Key Performance Indicator (KPI) A measurable value demonstrating how effectively objectives are being achieved.
Kickoff Meeting The initial meeting to formally start a project and align stakeholders.

L

Term Definition
Lag A delay between dependent tasks.
Lead An acceleration (overlap) between dependent tasks.
Lessons Learned Knowledge gained from project experiences to improve future performance.

M

Term Definition
Milestone A significant point or event in the project schedule.
Mitigation Actions taken to reduce the probability or impact of a risk.
MoSCoW A prioritisation technique: Must have, Should have, Could have, Won’t have.
MVP (Minimum Viable Product) The simplest version of a product that delivers value to users.

N

Term Definition
Non-Functional Requirements Specifications of how a system should perform (speed, security, usability).

O

Term Definition
OBS (Organisational Breakdown Structure) A hierarchy showing how resources are organised by team or function.
Opportunity A risk with a positive potential outcome.

P

Term Definition
PBS (Product Breakdown Structure) A hierarchy of products/deliverables to be created.
PERT Program Evaluation and Review Technique - a method for estimating task durations.
Phase A distinct stage in the project lifecycle.
PID (Project Initiation Document) A comprehensive document defining the project at the end of initiation.
PMO (Project Management Office) A department that defines and maintains PM standards across an organisation.
Portfolio A collection of programmes and projects managed together.
Probability The likelihood that a risk will occur.
Product Owner In Agile, the person responsible for maximising value and managing the backlog.
Programme A group of related projects managed together to achieve strategic benefits.
Project A temporary endeavour to create a unique product, service, or result.
PV (Planned Value) The authorised budget assigned to scheduled work.

Q

Term Definition
Quality Assurance (QA) Activities ensuring quality processes are being followed.
Quality Control (QC) Activities verifying deliverables meet quality standards.

R

Term Definition
RACI A matrix defining Responsible, Accountable, Consulted, and Informed roles.
RAG Status Red/Amber/Green indicator showing project health.
RAID Log A log tracking Risks, Assumptions, Issues, and Dependencies.
Requirements Statements describing what a solution must do or qualities it must have.
Resource People, equipment, materials, or budget needed for the project.
Retrospective A meeting to reflect on what went well and what to improve.
Risk An uncertain event that, if it occurs, would affect project objectives.
Risk Appetite The level of risk an organisation is willing to accept.
Risk Register A document listing identified risks with their assessment and response plans.
Roadmap A high-level visual timeline showing major deliverables and milestones.
ROI (Return on Investment) A measure of the profitability of an investment.

S

Term Definition
Scope The boundaries of what the project will and won’t deliver.
Scope Creep Uncontrolled expansion of project scope without corresponding changes to time, cost, or resources.
Scrum An Agile framework using sprints, daily stand-ups, and defined roles.
Scrum Master In Scrum, the person facilitating the process and removing impediments.
SPI (Schedule Performance Index) A measure of schedule efficiency: EV ÷ PV. Values >1 indicate ahead of schedule.
Sprint A time-boxed iteration in Scrum, typically 1-4 weeks.
Stakeholder Anyone who affects, is affected by, or perceives themselves affected by the project.
Stand-up A brief daily meeting for team coordination (also called Daily Scrum).
Steering Committee A governance body providing direction and decisions for a project or programme.

T

Term Definition
Timebox A fixed period during which work must be completed.
Tolerance Permitted deviation from a baseline before escalation is required.
Traceability The ability to track requirements through design, build, and test.

U

Term Definition
UAT (User Acceptance Testing) Testing by end users to confirm the solution meets business needs.
User Story In Agile, a requirement written from the user’s perspective: “As a [role], I want [goal], so that [benefit].”

V

Term Definition
Variance The difference between planned and actual performance.
Velocity In Agile, the amount of work a team completes in a sprint.

W

Term Definition
Waterfall A sequential project approach where each phase must complete before the next begins.
WBS (Work Breakdown Structure) A hierarchical decomposition of the project scope into manageable work packages.
Work Package The lowest level of the WBS, representing a defined piece of work.

X

Term Definition
XP (Extreme Programming) An Agile software development methodology emphasising technical practices.

Y

Term Definition
Yield The benefit or return generated by an investment or project.

Z

Term Definition
Zero Float A task with no schedule flexibility; any delay affects the project end date.

Common Acronyms

Acronym Full Term
AC Actual Cost
BAC Budget at Completion
BAU Business as Usual
BCM Business Change Management
CAPEX Capital Expenditure
CPI Cost Performance Index
CR Change Request
EAC Estimate at Completion
ETC Estimate to Complete
EV Earned Value
MVP Minimum Viable Product
NFR Non-Functional Requirement
OBS Organisational Breakdown Structure
OPEX Operating Expenditure
PBS Product Breakdown Structure
PID Project Initiation Document
PM Project Manager
PMO Project Management Office
PO Product Owner
PRINCE2 PRojects IN Controlled Environments
PV Planned Value
QA Quality Assurance
QC Quality Control
RACI Responsible, Accountable, Consulted, Informed
RAG Red, Amber, Green
RAID Risks, Assumptions, Issues, Dependencies
ROI Return on Investment
SM Scrum Master
SPI Schedule Performance Index
UAT User Acceptance Testing
WBS Work Breakdown Structure

Last updated: 13 January 2026