Introduction

Configuration management (CM) is the discipline of identifying, controlling, tracking, and verifying the products and deliverables of a project. It ensures that the project team — and the wider organisation — always knows exactly what has been produced, what version it is, how it relates to other items, and whether it has been properly approved.

CM is not just for software or engineering projects. Any project that produces deliverables — documents, designs, code, hardware, or services — benefits from a structured approach to configuration management.

What is Configuration Management?

Configuration management answers four fundamental questions:

  1. What do we have? — Identification of all configuration items
  2. What is its status? — Current version, approval state, and location
  3. What has changed? — Full history of changes and the reasons behind them
  4. Is it correct? — Verification that items match their approved specifications
flowchart LR A[Identification] --> B[Control] B --> C[Status Accounting] C --> D[Verification & Audit] D --> A classDef blue fill:#108BB9,stroke:none,color:#fff class A,B,C,D blue

Configuration Items

A configuration item (CI) is any component that is subject to configuration management. CIs can be documents, software modules, hardware components, or any other deliverable that needs to be controlled.

Types of Configuration Items

CI Type Examples
Management products Project plan, business case, risk register, RAID log
Technical products Requirements specification, design documents, test plans
Software Source code, executables, configuration files, scripts
Hardware Servers, network equipment, end-user devices
Services Cloud subscriptions, licences, support agreements
Baselines Approved sets of CIs at a defined point in time

CI Attributes

Each configuration item should be recorded with the following attributes:

Attribute Description
CI identifier Unique reference code
Name Descriptive name
Type / category Classification of the CI
Owner Person accountable for the CI
Version Current version number
Status Draft, approved, superseded, archived
Location Where the CI is stored
Relationships Links to related CIs (parent, child, dependency)
Baseline Which baseline(s) the CI belongs to

Configuration Management Plan

The configuration management plan (CMP) defines how CM will be implemented on the project. It should be created during the initiation phase and approved before delivery begins.

CMP Contents

Section Description
Purpose and scope What CM covers on this project
Roles and responsibilities Who performs CM activities
CI identification scheme Naming and numbering conventions
Configuration control process How changes are requested, assessed, and approved
Status accounting procedures How CI status is recorded and reported
Audit and verification approach How and when CM audits are conducted
Tools and infrastructure Systems used for CM
Baselines Planned baselines and their composition

The Four CM Activities

1. Configuration Identification

Identification involves defining and documenting the characteristics of each CI, including its relationships to other CIs.

Key tasks:

  • Define the CI identification and naming scheme
  • Select which items will be placed under configuration control
  • Document CI attributes in the configuration management database (CMDB) or register
  • Establish the CI hierarchy and relationships

2. Configuration Control

Configuration control ensures that changes to CIs are managed through a formal process. No change should be made to a baselined CI without proper authorisation.

flowchart LR A[Change Request
Raised] --> B[Impact
Assessment] B --> C[Change Authority
Decision] C -->|Approved| D[Implement
Change] C -->|Rejected| E[Close Request] D --> F[Update CI &
Version] F --> G[Update CMDB
& Baseline] classDef blue fill:#108BB9,stroke:none,color:#fff class A,B,C,D,E,F,G blue

Change authority levels:

Change Severity Authority
Minor (cosmetic, typographical) Document owner
Moderate (content, scope within tolerance) Project manager
Major (scope beyond tolerance, baseline change) Change control board / project board
Strategic (programme or portfolio impact) Programme board / portfolio board

3. Configuration Status Accounting

Status accounting is the recording and reporting of information needed to manage CIs effectively. It provides visibility of the current state of all CIs and their change history.

Status accounting outputs:

  • Current version and status of every CI
  • History of all changes including who, when, and why
  • Baseline composition and any deviations
  • Outstanding change requests and their status

4. Configuration Verification and Audit

Verification and audit confirm that the actual CIs match their documented descriptions. Audits can be functional (does the CI meet its requirements?) or physical (does the CI match its documented configuration?).

Audit Type Focus Timing
Functional audit Does the CI meet its requirements and specifications? Before baseline, at stage gates
Physical audit Does the physical CI match the documented configuration? Before deployment, at release
CM process audit Are CM processes being followed correctly? Periodic, or after incidents

Baselines

A baseline is a formally approved set of configuration items that serves as a reference point for future changes. Once a baseline is established, changes can only be made through the configuration control process.

Common Baselines

Baseline Content When Established
Requirements baseline Approved requirements specification End of requirements phase
Design baseline Approved design documents and architecture End of design phase
Build baseline Source code, build scripts, configuration Before testing
Test baseline Test plans, test cases, test data Before test execution
Release baseline Deployable package with all components Before go-live
Operational baseline Live configuration including infrastructure After go-live

Baseline Management

  • Each baseline is uniquely identified and recorded in the CMDB
  • The composition of each baseline is documented (which CIs, which versions)
  • Changes to baselined items trigger the change control process
  • Baselines can be compared to identify drift or unauthorised changes

Change Control Integration

Configuration management and change control are closely linked. Change control governs the decision to make a change; configuration management governs the implementation and tracking of that change.

Activity Change Control Configuration Management
Request a change  
Assess impact ✓ (identifies affected CIs)
Approve or reject  
Implement the change  
Update version and status  
Verify correctness  
Report status  

CM for Different Project Types

Traditional (Waterfall) Projects

  • Baselines established at each stage gate
  • Formal change control through a change control board
  • CMDB maintained as a register or spreadsheet for smaller projects

Agile Projects

  • Baselines established at each release or iteration
  • Change is managed through backlog refinement and sprint planning
  • Version control systems (e.g. Git) serve as the primary CM tool for software
  • Lighter-weight documentation with more emphasis on automated tracking

Infrastructure and Operations

  • CMDB is a core tool (often part of ITIL service management)
  • CIs include hardware, software, licences, and network components
  • Discovery tools automatically populate and verify the CMDB
  • Change management processes are tightly integrated

Roles and Responsibilities

Role Responsibilities
Configuration Manager Maintains the CMDB; administers CM processes; conducts audits
Project Manager Ensures CM plan is in place and followed; acts as change authority for moderate changes
Change Control Board Approves or rejects major changes to baselined CIs
CI Owner Accountable for the accuracy and currency of their CI
All team members Follow CM processes; raise change requests; do not make unauthorised changes

Getting Started Checklist

# Action Done?
1 Appoint a configuration manager or assign CM responsibilities
2 Define the CI identification and naming scheme
3 Identify all configuration items and record in a register
4 Establish the configuration management plan
5 Define the change control process for CIs
6 Set up the CMDB or configuration register
7 Establish the first baseline
8 Brief the team on CM processes and expectations
9 Schedule periodic CM audits
10 Integrate CM reporting into project status reports