PRINCE2 Fundamentals
PRINCE2 (Projects IN Controlled Environments) is a structured project management methodology widely used across industries worldwide. Originally developed by the UK government, it provides a flexible framework that can be tailored to any project size.
The PRINCE2 Structure
PRINCE2 is built on three integrated elements:
flowchart TB
subgraph principles["7 PRINCIPLES"]
P1["Guiding obligations"]
end
subgraph themes["7 THEMES"]
T1["Aspects to manage throughout"]
end
subgraph processes["7 PROCESSES"]
PR1["Steps from start to finish"]
end
principles --- themes --- processes
classDef blue fill:#108BB9,stroke:none,color:#fff
class P1,T1,PR1 blue
The 7 Principles
These are the guiding obligations that determine whether a project is genuinely using PRINCE2.
1. Continued Business Justification
- Every project must have a valid business reason
- Justification is documented in the Business Case
- Reviewed at each stage gate
- Project stops if justification no longer exists
2. Learn from Experience
- Lessons are sought from previous projects at the start
- Lessons are recorded throughout the project
- Lessons are passed on at project closure
- Supports continuous improvement
3. Defined Roles and Responsibilities
- Clear accountability at all levels
- Three primary interests: Business, User, Supplier
- Defined in the Project Management Team structure
- Everyone knows what they’re responsible for
4. Manage by Stages
- Project is planned and controlled stage by stage
- Senior management control at stage boundaries
- Provides regular review points
- Limits risk exposure
5. Manage by Exception
- Tolerances are set for time, cost, scope, quality, risk, benefits
- Escalation only when tolerances are forecast to be exceeded
- Empowers project manager within defined limits
- Efficient use of senior management time
6. Focus on Products
- Focus on defining and delivering products (outputs)
- Products must meet quality criteria
- Clear product descriptions
- Quality is planned, not inspected in
7. Tailor to the Environment
- PRINCE2 must be tailored to the project
- Consider size, complexity, risk, environment
- Avoid “PRINCE2 in a box” approach
- Document tailoring decisions
The 7 Themes
Themes are aspects of project management that must be addressed continuously throughout the project.
| Theme | Purpose | Key Question |
|---|---|---|
| Business Case | Establish viability | Why are we doing this? |
| Organisation | Define accountability | Who is involved? |
| Quality | Define and verify fitness | What do we need to deliver? |
| Plans | Define how, when, by whom | How will we achieve it? |
| Risk | Identify and manage uncertainty | What if…? |
| Change | Control changes to baseline | What’s the impact? |
| Progress | Monitor and compare | Where are we now? |
Business Case Theme
- Documents justification for the project
- Contains costs, benefits, risks, timescales
- Updated at each stage boundary
- Owned by the Executive
Organisation Theme
- Defines the project management team structure
- Project Board: Executive, Senior User, Senior Supplier
- Project Manager: Day-to-day management
- Team Manager: Delivering work packages
Quality Theme
- Quality planning: what, how, by whom
- Product Descriptions define acceptance criteria
- Quality control: inspections, reviews, testing
- Quality assurance: independent verification
Plans Theme
- Project Plan: High-level, whole project
- Stage Plan: Detailed, current stage
- Team Plan: Optional, work package level
- Exception Plan: Replaces current plan when tolerances exceeded
Risk Theme
- Risk identification, assessment, and response
- Risk Register tracks all identified risks
- Response types: Avoid, Reduce, Transfer, Accept, Share
- Continuous activity throughout project
Change Theme
- Issue Register captures all issues
- Issue types: Request for Change, Off-specification, Problem/Concern
- Change Authority may be delegated
- Configuration management maintains product integrity
Progress Theme
- Monitoring actual vs planned
- Checkpoint Reports: Team to PM (regular)
- Highlight Reports: PM to Board (periodic)
- Stage boundaries provide control points
The 7 Processes
Processes provide the steps for managing a project from start to finish.
flowchart TD
SU[Starting Up a Project\nSU] --> DP[Directing a Project\nDP]
DP --> IP[Initiating a Project\nIP]
IP --> CS[Controlling a Stage\nCS]
CS --> MP[Managing Product Delivery\nMP]
MP --> CS
CS --> SB[Managing a Stage Boundary\nSB]
SB --> DP
SB --> CS
SB --> CP[Closing a Project\nCP]
classDef blue fill:#108BB9,stroke:none,color:#fff
class SU,DP,IP,CS,MP,SB,CP blue
Starting Up a Project (SU)
- Appoint Executive and Project Manager
- Capture previous lessons
- Design project management team
- Prepare outline Business Case
- Select project approach
- Plan initiation stage
Directing a Project (DP)
- Project Board activities throughout
- Authorise initiation, stages, and closure
- Give ad hoc direction
- Final process: Authorise project closure
Initiating a Project (IP)
- Create Project Initiation Documentation (PID)
- Refine Business Case
- Create Project Plan
- Set up controls
- Assemble PID for approval
Controlling a Stage (CS)
- Day-to-day project manager activities
- Authorise work packages
- Review work package status
- Report highlights
- Capture and examine issues
- Escalate issues and risks
- Take corrective action
Managing Product Delivery (MP)
- Team Manager activities
- Accept work packages
- Execute work packages
- Deliver work packages
Managing a Stage Boundary (SB)
- Plan next stage
- Update Project Plan
- Update Business Case
- Report stage end
- Produce Exception Plan (if required)
Closing a Project (CP)
- Prepare planned or premature closure
- Hand over products
- Evaluate the project
- Recommend project closure
Key PRINCE2 Documents
| Document | Created | Purpose |
|---|---|---|
| Project Brief | SU | Initial project definition |
| Business Case | SU → Throughout | Justification for project |
| PID | IP | Complete project definition |
| Project Plan | IP | High-level plan |
| Stage Plan | IP/SB | Detailed stage plan |
| Work Package | CS | Authorisation to do work |
| Checkpoint Report | MP | Team progress report |
| Highlight Report | CS | PM to Board progress report |
| End Stage Report | SB | Stage summary |
| End Project Report | CP | Project summary |
| Lessons Report | CP | Lessons for future |
PRINCE2 Certification Path
| Level | Description | Prerequisite |
|---|---|---|
| Foundation | Understand terminology and method | None |
| Practitioner | Apply method to scenarios | Foundation |
| Agile Foundation | Understand PRINCE2 Agile | None |
| Agile Practitioner | Apply PRINCE2 Agile | Foundation or Agile Foundation |
Related Resources
- Methodologies Overview - Compare with other approaches
- Project Lifecycle - How PRINCE2 maps to lifecycle stages
- Project Initiation Document - PID template
- Hybrid Approaches - PRINCE2 Agile
- Risk Management Overview - Comprehensive risk management guide
- Risk Assessment Matrix - Risk scoring and prioritisation
- Risk Response Strategies - Avoid, Mitigate, Transfer, Accept
Last updated: 13 January 2026