Risk Assessment Matrix

A risk assessment matrix (also called a risk heat map or probability-impact matrix) is a visual tool for evaluating and prioritising risks based on their likelihood of occurring and potential impact.


The 5x5 Risk Matrix

The most common format uses a 5x5 grid with probability on one axis and impact on the other.

Probability Impact
Very Low (1) Low (2) Medium (3) High (4) Very High (5)
Very High (5) 5 10 15 20 25
High (4) 4 8 12 16 20
Medium (3) 3 6 9 12 15
Low (2) 2 4 6 8 10
Very Low (1) 1 2 3 4 5

Risk Zones

The matrix is typically divided into three zones based on the risk score:

Zone Score Range Response Typical Actions
Red (High) 15-25 Active management required Immediate response plan, escalate to sponsor, allocate contingency
Amber (Medium) 5-14 Monitor closely Develop mitigation plan, assign owner, regular review
Green (Low) 1-4 Accept or monitor Document in register, periodic review

How to Use the Matrix

Step 1: Identify Risks

Gather risks through brainstorming, interviews, checklists, and lessons learned.

Step 2: Assess Probability

Rate the likelihood of each risk occurring using a defined scale:

Rating Probability Description
5 Very High >80% - Almost certain to occur
4 High 60-80% - More likely than not
3 Medium 40-60% - Could go either way
2 Low 20-40% - Unlikely but possible
1 Very Low <20% - Rare occurrence

Step 3: Assess Impact

Rate the potential impact if the risk occurs:

Rating Impact Cost Impact Schedule Impact
5 Very High >20% budget >20% schedule
4 High 10-20% budget 10-20% schedule
3 Medium 5-10% budget 5-10% schedule
2 Low 1-5% budget 1-5% schedule
1 Very Low <1% budget <1% schedule

Step 4: Calculate Risk Score

Multiply probability by impact: Risk Score = P x I

Step 5: Plot on Matrix

Place each risk on the matrix and determine its zone.

Step 6: Prioritise Response

Focus attention on high-scoring risks first.


The 3x3 Risk Matrix

For simpler projects, a 3x3 matrix may be sufficient:

Probability Impact
Low Medium High
High Medium High Critical
Medium Low Medium High
Low Low Low Medium

Worked Example

Consider a software project with these identified risks:

Risk ID Risk Description P I Score Zone
R001 Key developer leaves 3 4 12 Amber
R002 Third-party API changes 2 5 10 Amber
R003 Requirements creep 4 4 16 Red
R004 Server hardware failure 1 5 5 Amber
R005 Testing delays 3 3 9 Amber
R006 Budget approval delayed 2 2 4 Green

Priority order: R003 (16) > R001 (12) > R002 (10) > R005 (9) > R004 (5) > R006 (4)


Best Practices

Do:

  • Use consistent scales across all projects
  • Involve the team in assessments
  • Consider multiple impact dimensions
  • Review and update regularly
  • Document assumptions behind ratings

Don’t:

  • Let one person assess all risks alone
  • Use overly complex scales
  • Ignore low-probability, high-impact risks
  • Forget to reassess after changes
  • Treat the matrix as static

Matrix Variations

Asymmetric Matrices

Some organisations weight impact more heavily than probability, creating asymmetric zones.

Multiple Impact Dimensions

Assess impact across several dimensions (cost, time, quality, reputation) and use the highest score.

Proximity Consideration

Add a third dimension for how soon the risk might occur (imminent risks may need faster response regardless of score).


Last updated: 13 January 2026