Project Toolkit

Project Reporting

Project Reporting

Communicating project status, progress, and issues to stakeholders.

Project Reporting

Project reporting communicates status, progress, risks, and issues to stakeholders, enabling informed decision-making.


Purpose

Effective project reporting:

  • Keeps stakeholders informed
  • Provides early warning of problems
  • Supports governance decisions
  • Creates accountability
  • Documents project history

Report Types

Report Audience Frequency Purpose
Highlight Report Project Board Weekly/Monthly Executive summary
Checkpoint Report PM/Team Lead Weekly Team progress
Exception Report Project Board As needed Tolerance breach
End Stage Report Project Board Stage end Stage assessment
End Project Report Project Board Project end Final assessment

Highlight Report Content

Section Content
Overall status RAG status with summary
Progress What was achieved this period
Plan What’s planned for next period
Milestones Status of key milestones
Budget Financial position
Risks Top risks and mitigations
Issues Open issues requiring attention
Decisions Decisions needed from board

RAG Status

flowchart LR R[RED
Off track] ~~~ A[AMBER
At risk] A ~~~ G[GREEN
On track] classDef blue fill:#108BB9,stroke:none,color:#fff class R,A,G blue
Status Meaning Action
Green On track to deliver Continue as planned
Amber At risk, corrective action underway Monitor closely
Red Off track, intervention needed Escalate for decisions

RAG Criteria

Dimension Green Amber Red
Schedule On plan < 2 weeks late > 2 weeks late
Budget Within tolerance < 10% variance > 10% variance
Scope As baselined Minor changes Major changes
Quality Meeting standards Minor concerns Significant issues

Reporting Cadence

Level Report Frequency
Team Stand-up Daily
Team Lead Checkpoint Weekly
Project Board Highlight Weekly/Fortnightly
Programme Dashboard Monthly
Portfolio Summary Monthly

Effective Reporting Principles

  1. Be honest - Report reality, not hope
  2. Be timely - Deliver when expected
  3. Be concise - Respect readers’ time
  4. Be consistent - Use standard formats
  5. Be actionable - Highlight decisions needed
  6. Be balanced - Include successes and issues

Exception Reporting

flowchart LR A[Tolerance
Breach] --> B[Assess
Impact] B --> C[Develop
Options] C --> D[Raise
Exception] D --> E[Board
Decision] classDef blue fill:#108BB9,stroke:none,color:#fff class A,B,C,D,E blue

Exception reports are raised when:

  • Forecast exceeds tolerance
  • Major risk materialises
  • Significant issue cannot be resolved
  • External factors affect delivery

Exception Report Content

  • Nature of the exception
  • Impact on objectives
  • Options with pros/cons
  • Recommended action
  • Decision required

Dashboard Elements

Element Purpose
Status summary Quick visual overview
Milestone tracker Progress against plan
Budget chart Financial position
Risk heatmap Risk exposure
Issue count Outstanding issues
Trend indicators Direction of travel

Common Reporting Pitfalls

Pitfall Mitigation
Watermelon reporting (green outside, red inside) Be transparent, report issues early
Information overload Focus on key messages
Late reports Set up regular cadence
Inconsistent formats Use templates
No action focus Clearly state decisions needed
Reporting without data Base status on evidence

Reporting Checklist

  • Report audience defined?
  • Reporting cadence agreed?
  • Templates in place?
  • RAG criteria established?
  • Tolerance thresholds set?
  • Distribution list confirmed?
  • Review process established?

Status Report Templates

Different audiences need different report formats. Below are detailed templates for various reporting needs.


Weekly Status Report

The weekly status report is your primary communication tool with sponsors and key stakeholders.

Structure

Section Content Length
Header Project name, date, PM name, overall RAG 1 line
Executive summary 2-3 sentences on status 50 words
Progress this week Completed activities 3-5 bullets
Plan for next week Upcoming activities 3-5 bullets
Milestones Status of nearest milestones Table
Risks & Issues Top items requiring attention 3-5 items
Decisions needed Items requiring stakeholder input As needed

Weekly Status Report Example

PROJECT STATUS REPORT
=====================
Project: Customer Portal Redesign
Report Date: 13 January 2026
Project Manager: Jane Smith
Overall Status: AMBER

EXECUTIVE SUMMARY
The project remains on track for the April go-live.
User testing feedback has been positive but identified
accessibility issues requiring additional sprint work.

PROGRESS THIS WEEK
• Completed user acceptance testing (UAT) for Phase 1
• Resolved 12 of 15 critical defects from testing
• Finalised training materials for support team
• Secured sign-off on data migration approach

PLANNED NEXT WEEK
• Begin UAT for Phase 2 functionality
• Complete accessibility remediation
• Conduct pilot training session
• Finalise go-live communication plan

MILESTONE STATUS
| Milestone              | Planned    | Status  |
|------------------------|------------|---------|
| UAT Complete           | 20 Jan     | On Track|
| Training Complete      | 27 Jan     | On Track|
| Go-Live                | 1 April    | On Track|

TOP RISKS & ISSUES
1. [RISK] Resource availability during February
   holidays - Mitigation: Cross-training in progress
2. [ISSUE] Accessibility compliance gaps -
   Action: Additional 2-day sprint scheduled
3. [RISK] Third-party API stability -
   Mitigation: Fallback solution documented

DECISIONS NEEDED
• Approve revised accessibility timeline (adds 3 days)
• Confirm pilot group for soft launch

Monthly Progress Report

Monthly reports provide a comprehensive view for governance and senior management.

Structure

Section Content Detail Level
Executive summary Overall status, key achievements, concerns High-level
Schedule status Progress against plan, milestone tracking Detailed
Budget status Spend vs plan, forecast, variances Detailed
Scope status Deliverable progress, change requests Moderate
Risk summary Risk profile, top risks, changes Moderate
Issue summary Open issues, resolutions, escalations Moderate
Resource status Team utilisation, capacity issues Summary
Quality status Defect metrics, testing progress Summary
Next period focus Key activities, decisions needed Forward-looking
Appendices Detailed data, supporting information As needed

Monthly Report Sections Explained

Executive Summary Format:

Overall Status: [RAG]

This month: [2-3 sentence summary of achievements]

Key concerns: [Top 1-2 issues requiring attention]

Looking ahead: [Primary focus for next month]

Schedule Status Format:

Metric Value Trend
Planned % Complete 45% -
Actual % Complete 42%
Schedule Variance -3 days
Schedule Performance Index (SPI) 0.93

Budget Status Format:

Category Budget Actual Committed Forecast Variance
Labour £50,000 £22,000 £15,000 £48,000 £2,000
Software £10,000 £10,000 £0 £10,000 £0
Services £5,000 £2,000 £2,500 £5,500 -£500
Total £65,000 £34,000 £17,500 £63,500 £1,500

Executive Summary Report

For senior executives who need information quickly. Use the pyramid principle - lead with the conclusion.

One-Page Executive Format

flowchart TD A[Overall Status
& Key Message] --> B[Schedule] A --> C[Budget] A --> D[Risks] B --> E[Details on Request] C --> E D --> E classDef blue fill:#108BB9,stroke:none,color:#fff class A,B,C,D,E blue

Executive Report Template

PROJECT: [Name]                     DATE: [Date]
SPONSOR: [Name]                     PM: [Name]

┌─────────────────────────────────────────────────┐
│  OVERALL STATUS: [GREEN/AMBER/RED]              │
│                                                 │
│  [One sentence: Are we on track to deliver      │
│   the expected benefits on time and budget?]   │
└─────────────────────────────────────────────────┘

KEY METRICS
┌──────────┬──────────┬──────────┐
│ SCHEDULE │  BUDGET  │  SCOPE   │
│  [RAG]   │  [RAG]   │  [RAG]   │
│  +2 days │  -£5k    │ Baselined│
└──────────┴──────────┴──────────┘

THIS MONTH'S ACHIEVEMENTS
• [Major achievement 1]
• [Major achievement 2]

ATTENTION REQUIRED
• [Issue or decision needed]

NEXT MILESTONE
[Milestone name] - [Date] - [RAG status]

RAG Dashboard Report

Visual dashboard format for quick status communication.

Dashboard Components

Component Purpose Visual Format
Traffic lights Quick status read Coloured circles
Progress bar % complete visual Horizontal bar
Trend arrows Direction of travel ↑ → ↓ indicators
Milestone tracker Timeline visual Gantt-style
Risk heatmap Risk distribution Colour matrix
Burn-down chart Work remaining Line chart

Dashboard Layout

┌─────────────────────────────────────────────────────┐
│  PROJECT DASHBOARD - [Name] - [Date]                │
├─────────────────────────────────────────────────────┤
│                                                     │
│  OVERALL    SCHEDULE    BUDGET      SCOPE          │
│    🟢          🟡         🟢          🟢            │
│                                                     │
├─────────────────────────────────────────────────────┤
│  PROGRESS                                           │
│  ████████████████████░░░░░░░░░░  65%               │
│                                                     │
├─────────────────────────────────────────────────────┤
│  MILESTONES                                         │
│  ✓ Requirements    ✓ Design    ● Build    ○ Test   │
│  [Complete]       [Complete]  [Current]  [Pending] │
│                                                     │
├─────────────────────────────────────────────────────┤
│  TOP RISKS              │  OPEN ISSUES             │
│  • Resource capacity    │  • Integration delay     │
│  • Vendor dependency    │  • Test environment      │
│  • Timeline pressure    │                          │
└─────────────────────────────────────────────────────┘

Stakeholder-Specific Reports

Tailor your reports to different audiences:

Report by Audience Type

Audience Focus Format Frequency
Board/Executives Strategic, decisions 1-page summary Monthly
Sponsor Progress, issues, support Detailed status Weekly
Steering Committee Governance, risks Highlight report Fortnightly
Programme Manager Dependencies, resources Programme roll-up Weekly
Team Members Tasks, blockers Stand-up format Daily
End Users Impact, timeline Newsletter style As needed
Finance Budget, forecast Financial detail Monthly

Adapting Content by Audience

Content Executive Sponsor Team
Overall status ✓ Essential ✓ Essential ○ Brief
Schedule detail ○ Summary ✓ Detailed ✓ Detailed
Budget detail ○ Variance only ✓ Full breakdown ✗ Not needed
Risk detail ○ Top 3 ✓ All significant ○ Relevant only
Technical detail ✗ Avoid ○ As needed ✓ Essential
Dependencies ✗ Unless blocked ✓ All external ✓ Immediate

Stand-Up Report Format

For daily team coordination:

Three Questions

Question Purpose Time
What did you complete yesterday? Track progress 30 sec
What will you work on today? Coordinate effort 30 sec
Any blockers? Surface issues 30 sec

Stand-Up Board Format

┌─────────────┬─────────────┬─────────────┐
│   TO DO     │ IN PROGRESS │    DONE     │
├─────────────┼─────────────┼─────────────┤
│ • Task E    │ • Task C    │ • Task A    │
│ • Task F    │ • Task D    │ • Task B    │
│ • Task G    │             │             │
└─────────────┴─────────────┴─────────────┘

BLOCKERS: [Team member] blocked on [issue]
          [Team member] waiting for [dependency]

Exception Report Template

When tolerances are breached or significant issues arise:

Exception Report Structure

Section Content
Exception description What has happened or is forecast
Cause Root cause of the exception
Impact Effect on time, cost, scope, benefits
Options Possible responses with pros/cons
Recommendation Preferred option with rationale
Decision required Specific ask of the board

Exception Report Example

EXCEPTION REPORT
================
Project: Customer Portal Redesign
Date: 13 January 2026
Exception Type: Schedule

EXCEPTION DESCRIPTION
The project is forecast to exceed the approved
end date by 3 weeks due to additional accessibility
compliance requirements.

CAUSE
New WCAG 2.2 guidelines published after project
approval require additional development work not
in original scope.

IMPACT
• Schedule: +3 weeks (new end date: 22 April)
• Cost: +£8,000 for additional development
• Benefits: Delayed by 3 weeks
• Quality: Improved accessibility compliance

OPTIONS

Option 1: Extend timeline (Recommended)
• Accept 3-week delay
• Additional £8,000 cost
• Full compliance achieved
• Pros: Complete solution, reduced risk
• Cons: Delayed benefits

Option 2: Reduce scope
• Remove 2 non-critical features
• Maintain original timeline
• Pros: On-time delivery
• Cons: Reduced functionality

Option 3: Increase resources
• Add 2 contractors for 4 weeks
• Additional £15,000 cost
• Maintain timeline
• Pros: Full scope on time
• Cons: Higher cost, integration risk

RECOMMENDATION
Option 1 - The 3-week delay has minimal business
impact and ensures full accessibility compliance,
reducing legal and reputational risk.

DECISION REQUIRED
Approve revised end date of 22 April 2026 and
additional budget of £8,000.

Report Writing Tips

Tip Explanation
Lead with the headline Put the most important information first
Use consistent structure Same format every time for easy scanning
Be specific with numbers “42% complete” not “making good progress”
Highlight changes What’s different from last report
Separate fact from opinion Clear distinction between data and assessment
Include actions and owners Every issue should have a next step
Keep it visual Use tables, charts, and RAG indicators
Proofread Errors undermine credibility

Report Distribution Matrix

Report Owner Reviewers Distribution Archive
Weekly Status PM Sponsor Stakeholder list SharePoint
Monthly Progress PM PMO Board + sponsors SharePoint
Exception PM Sponsor Board SharePoint
Dashboard PM - Self-service Live system

Last updated: 13 January 2026