Backout Plan

Backout Plan

Contingency plan to reverse a deployment or implementation if critical issues arise, ensuring business continuity and minimal disruption.

Backout Plan

A Backout Plan documents how to reverse a deployment or implementation if critical issues are encountered, providing a safety net that enables confident go-live decisions.


Purpose

The Backout Plan:

  • Provides a safety net for deployment
  • Defines criteria for triggering rollback
  • Documents step-by-step reversal process
  • Assigns responsibilities for execution
  • Enables confident go/no-go decisions
  • Minimises business disruption

When to Create

Situation Backout Required
Major deployment Yes
System upgrade Yes
Database changes Yes
Integration changes Yes
Process changes Consider
Configuration changes Consider
Minor patches Risk-based

Backout Decision Framework

flowchart TD A[Issue
Detected] --> B{Severity?} B -->|Critical| C[Invoke
Backout] B -->|Major| D{Fixable in
Window?} B -->|Minor| E[Log &
Continue] D -->|Yes| F[Fix
Forward] D -->|No| C C --> G[Execute
Backout] G --> H[Verify
Reversal] H --> I[Post-Backout
Review] classDef blue fill:#108BB9,stroke:none,color:#fff class A,B,C,D,E,F,G,H,I blue

Backout Plan Template

Plan Header

Field Content
Project Customer Portal Enhancement
Release Release 2.0
Deployment Date 07 June 2026
Plan Owner John Smith (PM)
Version 1.2
Status Approved

Deployment Overview

Element Details
What is being deployed Customer Portal v2.0
Components affected Web application, database, APIs
Environments Production
Deployment window 02:00-06:00 Saturday
Backout window By 06:00 Saturday

Backout Triggers

Trigger Criteria

Severity Criteria Action
Critical System unavailable Immediate backout
Critical Data corruption Immediate backout
Critical Security breach Immediate backout
Major Core function broken Backout if not fixable
Major Performance degradation >50% Backout if not fixable
Minor Non-critical defect Log and fix later

Specific Triggers for This Release

# Trigger Threshold
1 Login failure rate >5%
2 Transaction errors >2%
3 Page load time >10 seconds
4 API response time >5 seconds
5 Error rate >1%
6 Database connectivity Any failure

Backout Decision Authority

Decision Matrix

Severity Decision Maker Notification
Critical Deployment Lead PM, Sponsor
Major PM Sponsor
Discretionary Sponsor Steering Group

Contact List

Role Name Phone Availability
Deployment Lead Jane Doe xxx-xxxx On-site
Project Manager John Smith xxx-xxxx On-call
Sponsor Sarah Williams xxx-xxxx On-call
IT Operations Dave Jones xxx-xxxx On-site
DBA Mike Brown xxx-xxxx On-call

Pre-Backout Requirements

Before Deployment

Requirement Owner Status
Database backup complete DBA
Application backup complete Ops
Configuration backup Ops
Backout scripts tested Dev
Rollback verified in staging QA
Team briefed on backout PM

Backup Details

Component Backup Location Verified
Database /backup/db/portal_20260607
Application files /backup/app/portal_v1.9
Configuration /backup/config/portal_20260607
Load balancer config /backup/lb/portal_20260607

Backout Procedure

Step-by-Step Process

Step Action Owner Duration Verify
1 Announce backout to team PM 2 min Team notified
2 Stop incoming traffic Ops 5 min No new connections
3 Notify users (if applicable) Support 5 min Message displayed
4 Stop application servers Ops 5 min Services stopped
5 Restore database DBA 30 min DB restored
6 Restore application Ops 15 min Files restored
7 Restore configuration Ops 10 min Config restored
8 Start application servers Ops 5 min Services started
9 Verify system health QA 15 min All checks pass
10 Resume traffic Ops 5 min System live
11 Notify stakeholders PM 5 min Comms sent
Total     ~100 min  

Detailed Steps

Step 1: Announce Backout

Action: Announce backout decision to deployment team
Owner: Project Manager
Commands/Actions:
- Call: "Backout invoked. All team members standby."
- Confirm: Each team member acknowledges
Verification: Verbal confirmation from all team members

Step 5: Restore Database

Action: Restore database from pre-deployment backup
Owner: DBA
Commands:
1. Stop database connections
   $ sqlplus / as sysdba
   SQL> ALTER SYSTEM KILL SESSION 'sid,serial#';

2. Restore from backup
   $ rman target /
   RMAN> RESTORE DATABASE;
   RMAN> RECOVER DATABASE;

3. Open database
   SQL> ALTER DATABASE OPEN RESETLOGS;

Verification:
- Run: SELECT COUNT(*) FROM customers;
- Expected: Match pre-deployment count
- Run: SELECT version FROM system_info;
- Expected: v1.9

Step 6: Restore Application

Action: Restore application files from backup
Owner: Operations
Commands:
1. Stop application
   $ systemctl stop portal

2. Remove deployed version
   $ rm -rf /opt/portal/current/*

3. Restore previous version
   $ cp -r /backup/app/portal_v1.9/* /opt/portal/current/

4. Verify files
   $ ls -la /opt/portal/current/

Verification:
- File count matches backup
- Version file shows v1.9

Post-Backout Actions

Immediate Actions

Action Owner Timeframe
Verify system operational QA Immediately
Notify stakeholders PM Within 30 min
Document what happened PM Within 2 hours
Schedule post-mortem PM Within 24 hours

Communication

Audience Message Channel Owner
Users Service restored, apology Banner/email Support
Stakeholders Status update Email PM
Management Incident summary Email PM
Team Debrief meeting Meeting PM

Post-Backout Review

Question Response
What triggered the backout?  
Was the trigger appropriate?  
Did backout execute as planned?  
What was the actual duration?  
What could be improved?  
Root cause of original issue?  
Plan for next attempt?  

Testing the Backout

Pre-Deployment Testing

Test Environment Status
Full backout rehearsal Staging
Database restore test Staging
Application restore test Staging
End-to-end verification Staging
Time the backout Staging

Test Results

Test Expected Duration Actual Duration Issues
Database restore 30 min    
Application restore 15 min    
Total backout 100 min    
Verification 15 min    

Risk Considerations

Backout Risks

Risk Mitigation
Backup corruption Test backups before deployment
Incomplete restore Verify all components in staging
Data loss (new transactions) Minimal deployment window
Team unavailable Clear on-call roster
Unknown dependencies Thorough impact analysis

Cannot Backout Scenarios

Scenario Alternative
Database schema incompatible Data migration scripts
Third-party changes Coordinate with vendor
Distributed systems Coordinated rollback
Data loss unacceptable Forward-fix only

Alternative Strategies

Fix-Forward vs Backout

Factor Favour Fix-Forward Favour Backout
Time to fix Quick (<1 hour) Long (>2 hours)
Confidence High Low
Risk Low High
Business impact Moderate Severe
Data integrity No risk At risk

Partial Backout

Scenario Approach
Single component failure Rollback that component only
Feature-specific issue Disable feature via config
Performance issue Scale down, investigate

Documentation

During Backout

Document Owner
Timeline of events PM
Commands executed Ops
Issues encountered All
Decisions made PM

After Backout

Document Purpose Owner
Incident report Official record PM
Root cause analysis Understanding Tech Lead
Updated backout plan Improvement PM
Lessons learned Future reference PM

Backout Plan Checklist

Planning Phase

  • Components identified?
  • Backup procedures defined?
  • Restore procedures documented?
  • Triggers defined?
  • Decision authority clear?
  • Contact list current?
  • Team briefed?

Pre-Deployment

  • Backups completed?
  • Backups verified?
  • Scripts tested?
  • Team available?
  • Communication ready?

During Deployment

  • Monitoring active?
  • Team on standby?
  • Triggers being checked?
  • Communication channels open?

Post-Backout (if invoked)

  • System verified?
  • Stakeholders notified?
  • Incident documented?
  • Post-mortem scheduled?
  • Plan updated?

Last updated: 13 January 2026