Backout Plan
Contingency plan to reverse a deployment or implementation if critical issues arise, ensuring business continuity and minimal disruption.
Backout Plan
A Backout Plan documents how to reverse a deployment or implementation if critical issues are encountered, providing a safety net that enables confident go-live decisions.
Purpose
The Backout Plan:
- Provides a safety net for deployment
- Defines criteria for triggering rollback
- Documents step-by-step reversal process
- Assigns responsibilities for execution
- Enables confident go/no-go decisions
- Minimises business disruption
When to Create
| Situation | Backout Required |
|---|---|
| Major deployment | Yes |
| System upgrade | Yes |
| Database changes | Yes |
| Integration changes | Yes |
| Process changes | Consider |
| Configuration changes | Consider |
| Minor patches | Risk-based |
Backout Decision Framework
flowchart TD
A[Issue
Detected] --> B{Severity?} B -->|Critical| C[Invoke
Backout] B -->|Major| D{Fixable in
Window?} B -->|Minor| E[Log &
Continue] D -->|Yes| F[Fix
Forward] D -->|No| C C --> G[Execute
Backout] G --> H[Verify
Reversal] H --> I[Post-Backout
Review] classDef blue fill:#108BB9,stroke:none,color:#fff class A,B,C,D,E,F,G,H,I blue
Detected] --> B{Severity?} B -->|Critical| C[Invoke
Backout] B -->|Major| D{Fixable in
Window?} B -->|Minor| E[Log &
Continue] D -->|Yes| F[Fix
Forward] D -->|No| C C --> G[Execute
Backout] G --> H[Verify
Reversal] H --> I[Post-Backout
Review] classDef blue fill:#108BB9,stroke:none,color:#fff class A,B,C,D,E,F,G,H,I blue
Backout Plan Template
Plan Header
| Field | Content |
|---|---|
| Project | Customer Portal Enhancement |
| Release | Release 2.0 |
| Deployment Date | 07 June 2026 |
| Plan Owner | John Smith (PM) |
| Version | 1.2 |
| Status | Approved |
Deployment Overview
| Element | Details |
|---|---|
| What is being deployed | Customer Portal v2.0 |
| Components affected | Web application, database, APIs |
| Environments | Production |
| Deployment window | 02:00-06:00 Saturday |
| Backout window | By 06:00 Saturday |
Backout Triggers
Trigger Criteria
| Severity | Criteria | Action |
|---|---|---|
| Critical | System unavailable | Immediate backout |
| Critical | Data corruption | Immediate backout |
| Critical | Security breach | Immediate backout |
| Major | Core function broken | Backout if not fixable |
| Major | Performance degradation >50% | Backout if not fixable |
| Minor | Non-critical defect | Log and fix later |
Specific Triggers for This Release
| # | Trigger | Threshold |
|---|---|---|
| 1 | Login failure rate | >5% |
| 2 | Transaction errors | >2% |
| 3 | Page load time | >10 seconds |
| 4 | API response time | >5 seconds |
| 5 | Error rate | >1% |
| 6 | Database connectivity | Any failure |
Backout Decision Authority
Decision Matrix
| Severity | Decision Maker | Notification |
|---|---|---|
| Critical | Deployment Lead | PM, Sponsor |
| Major | PM | Sponsor |
| Discretionary | Sponsor | Steering Group |
Contact List
| Role | Name | Phone | Availability |
|---|---|---|---|
| Deployment Lead | Jane Doe | xxx-xxxx | On-site |
| Project Manager | John Smith | xxx-xxxx | On-call |
| Sponsor | Sarah Williams | xxx-xxxx | On-call |
| IT Operations | Dave Jones | xxx-xxxx | On-site |
| DBA | Mike Brown | xxx-xxxx | On-call |
Pre-Backout Requirements
Before Deployment
| Requirement | Owner | Status |
|---|---|---|
| Database backup complete | DBA | ☐ |
| Application backup complete | Ops | ☐ |
| Configuration backup | Ops | ☐ |
| Backout scripts tested | Dev | ☐ |
| Rollback verified in staging | QA | ☐ |
| Team briefed on backout | PM | ☐ |
Backup Details
| Component | Backup Location | Verified |
|---|---|---|
| Database | /backup/db/portal_20260607 | ☐ |
| Application files | /backup/app/portal_v1.9 | ☐ |
| Configuration | /backup/config/portal_20260607 | ☐ |
| Load balancer config | /backup/lb/portal_20260607 | ☐ |
Backout Procedure
Step-by-Step Process
| Step | Action | Owner | Duration | Verify |
|---|---|---|---|---|
| 1 | Announce backout to team | PM | 2 min | Team notified |
| 2 | Stop incoming traffic | Ops | 5 min | No new connections |
| 3 | Notify users (if applicable) | Support | 5 min | Message displayed |
| 4 | Stop application servers | Ops | 5 min | Services stopped |
| 5 | Restore database | DBA | 30 min | DB restored |
| 6 | Restore application | Ops | 15 min | Files restored |
| 7 | Restore configuration | Ops | 10 min | Config restored |
| 8 | Start application servers | Ops | 5 min | Services started |
| 9 | Verify system health | QA | 15 min | All checks pass |
| 10 | Resume traffic | Ops | 5 min | System live |
| 11 | Notify stakeholders | PM | 5 min | Comms sent |
| Total | ~100 min |
Detailed Steps
Step 1: Announce Backout
Action: Announce backout decision to deployment team
Owner: Project Manager
Commands/Actions:
- Call: "Backout invoked. All team members standby."
- Confirm: Each team member acknowledges
Verification: Verbal confirmation from all team members
Step 5: Restore Database
Action: Restore database from pre-deployment backup
Owner: DBA
Commands:
1. Stop database connections
$ sqlplus / as sysdba
SQL> ALTER SYSTEM KILL SESSION 'sid,serial#';
2. Restore from backup
$ rman target /
RMAN> RESTORE DATABASE;
RMAN> RECOVER DATABASE;
3. Open database
SQL> ALTER DATABASE OPEN RESETLOGS;
Verification:
- Run: SELECT COUNT(*) FROM customers;
- Expected: Match pre-deployment count
- Run: SELECT version FROM system_info;
- Expected: v1.9
Step 6: Restore Application
Action: Restore application files from backup
Owner: Operations
Commands:
1. Stop application
$ systemctl stop portal
2. Remove deployed version
$ rm -rf /opt/portal/current/*
3. Restore previous version
$ cp -r /backup/app/portal_v1.9/* /opt/portal/current/
4. Verify files
$ ls -la /opt/portal/current/
Verification:
- File count matches backup
- Version file shows v1.9
Post-Backout Actions
Immediate Actions
| Action | Owner | Timeframe |
|---|---|---|
| Verify system operational | QA | Immediately |
| Notify stakeholders | PM | Within 30 min |
| Document what happened | PM | Within 2 hours |
| Schedule post-mortem | PM | Within 24 hours |
Communication
| Audience | Message | Channel | Owner |
|---|---|---|---|
| Users | Service restored, apology | Banner/email | Support |
| Stakeholders | Status update | PM | |
| Management | Incident summary | PM | |
| Team | Debrief meeting | Meeting | PM |
Post-Backout Review
| Question | Response |
|---|---|
| What triggered the backout? | |
| Was the trigger appropriate? | |
| Did backout execute as planned? | |
| What was the actual duration? | |
| What could be improved? | |
| Root cause of original issue? | |
| Plan for next attempt? |
Testing the Backout
Pre-Deployment Testing
| Test | Environment | Status |
|---|---|---|
| Full backout rehearsal | Staging | ☐ |
| Database restore test | Staging | ☐ |
| Application restore test | Staging | ☐ |
| End-to-end verification | Staging | ☐ |
| Time the backout | Staging | ☐ |
Test Results
| Test | Expected Duration | Actual Duration | Issues |
|---|---|---|---|
| Database restore | 30 min | ||
| Application restore | 15 min | ||
| Total backout | 100 min | ||
| Verification | 15 min |
Risk Considerations
Backout Risks
| Risk | Mitigation |
|---|---|
| Backup corruption | Test backups before deployment |
| Incomplete restore | Verify all components in staging |
| Data loss (new transactions) | Minimal deployment window |
| Team unavailable | Clear on-call roster |
| Unknown dependencies | Thorough impact analysis |
Cannot Backout Scenarios
| Scenario | Alternative |
|---|---|
| Database schema incompatible | Data migration scripts |
| Third-party changes | Coordinate with vendor |
| Distributed systems | Coordinated rollback |
| Data loss unacceptable | Forward-fix only |
Alternative Strategies
Fix-Forward vs Backout
| Factor | Favour Fix-Forward | Favour Backout |
|---|---|---|
| Time to fix | Quick (<1 hour) | Long (>2 hours) |
| Confidence | High | Low |
| Risk | Low | High |
| Business impact | Moderate | Severe |
| Data integrity | No risk | At risk |
Partial Backout
| Scenario | Approach |
|---|---|
| Single component failure | Rollback that component only |
| Feature-specific issue | Disable feature via config |
| Performance issue | Scale down, investigate |
Documentation
During Backout
| Document | Owner |
|---|---|
| Timeline of events | PM |
| Commands executed | Ops |
| Issues encountered | All |
| Decisions made | PM |
After Backout
| Document | Purpose | Owner |
|---|---|---|
| Incident report | Official record | PM |
| Root cause analysis | Understanding | Tech Lead |
| Updated backout plan | Improvement | PM |
| Lessons learned | Future reference | PM |
Backout Plan Checklist
Planning Phase
- Components identified?
- Backup procedures defined?
- Restore procedures documented?
- Triggers defined?
- Decision authority clear?
- Contact list current?
- Team briefed?
Pre-Deployment
- Backups completed?
- Backups verified?
- Scripts tested?
- Team available?
- Communication ready?
During Deployment
- Monitoring active?
- Team on standby?
- Triggers being checked?
- Communication channels open?
Post-Backout (if invoked)
- System verified?
- Stakeholders notified?
- Incident documented?
- Post-mortem scheduled?
- Plan updated?
Related Resources
- Implementation Approach - Deployment strategy
- Service Transition - Go-live planning
- Risk Register - Risk management
- Test Approach - Testing strategy
- Support Model - Operational support
Last updated: 13 January 2026