Project Toolkit
Financial Forecasting
Predicting project costs to completion and managing financial variance.
Financial Forecasting
Financial forecasting predicts the final cost of the project based on current performance and remaining work.
Purpose
Financial forecasting enables:
- Early warning of budget issues
- Informed decision-making
- Proactive cost management
- Stakeholder confidence
- Accurate reporting to governance
Key Forecast Metrics
| Metric | Description |
|---|---|
| Budget | Approved funding |
| Actual | Costs incurred to date |
| Committed | Contracted but not yet spent |
| Forecast | Predicted total cost |
| Variance | Difference from budget |
| EAC | Estimate at Completion |
| ETC | Estimate to Complete |
Forecasting Process
flowchart LR
A[Gather
Actuals] --> B[Review
Commitments] B --> C[Estimate
Remaining] C --> D[Calculate
Forecast] D --> E[Analyse
Variance] E --> F[Report &
Action] classDef blue fill:#108BB9,stroke:none,color:#fff class A,B,C,D,E,F blue
Actuals] --> B[Review
Commitments] B --> C[Estimate
Remaining] C --> D[Calculate
Forecast] D --> E[Analyse
Variance] E --> F[Report &
Action] classDef blue fill:#108BB9,stroke:none,color:#fff class A,B,C,D,E,F blue
Calculating EAC (Estimate at Completion)
Method 1: Bottom-up
EAC = Actual + Estimate to Complete
Re-estimate remaining work based on current understanding.
Method 2: Based on current performance
EAC = Budget / Cost Performance Index (CPI)
Assumes future performance matches current trend.
Method 3: Based on remaining budget
EAC = Actual + (Budget - Earned Value)
Assumes remaining work will be completed at budget rate.
Earned Value Forecasting
| Metric | Formula | Meaning |
|---|---|---|
| CPI | EV / AC | Cost efficiency |
| SPI | EV / PV | Schedule efficiency |
| EAC | BAC / CPI | Forecast total cost |
| ETC | EAC - AC | Remaining cost |
| VAC | BAC - EAC | Variance at completion |
Interpreting CPI
| CPI | Meaning |
|---|---|
| > 1.0 | Under budget |
| = 1.0 | On budget |
| < 1.0 | Over budget |
Forecast Accuracy
Forecast accuracy typically improves over time:
| Project Phase | Accuracy Range |
|---|---|
| Initiation | ±50% |
| Planning | ±25% |
| Early Delivery | ±15% |
| Mid Delivery | ±10% |
| Late Delivery | ±5% |
Variance Analysis
When forecast differs from budget:
| Question | Purpose |
|---|---|
| What is the variance? | Quantify the gap |
| Why did it occur? | Identify root cause |
| Is it one-off or trend? | Assess future impact |
| Can it be recovered? | Identify corrective actions |
| What decisions are needed? | Inform governance |
Managing Cost Overruns
| Option | Description |
|---|---|
| Reduce scope | Defer or remove features |
| Improve efficiency | Optimise delivery approach |
| Use contingency | Draw on risk reserve |
| Request more funding | Seek budget increase |
| Accept variance | Proceed with known overrun |
Forecast Report Content
| Section | Content |
|---|---|
| Summary | Key figures and RAG status |
| Actuals | What’s been spent |
| Commitments | What’s contracted |
| Forecast | Predicted total |
| Variance | Comparison to budget |
| Trend | Direction of travel |
| Actions | Corrective measures |
| Risks | Financial risks and mitigations |
Forecasting Frequency
| Phase | Frequency |
|---|---|
| Initiation | Monthly |
| Planning | Fortnightly |
| Delivery | Weekly |
| Go-live | Daily |
Common Pitfalls
| Pitfall | Mitigation |
|---|---|
| Optimistic forecasting | Use data, not hope |
| Ignoring commitments | Track all contracted spend |
| Infrequent updates | Forecast regularly |
| Not investigating variance | Always understand the why |
| Hiding bad news | Report honestly and early |
Forecasting Checklist
- Actuals collected and reconciled?
- Commitments identified?
- Remaining work estimated?
- EAC calculated?
- Variance explained?
- Trends identified?
- Actions defined?
- Report distributed?
Related Resources
- Financial Planning - Budget development
- Project Reporting - Status reporting
- Risk Management - Risk reserves
- Project Board - Financial governance
Last updated: 13 January 2026
Themes
Forecasting
Financial