End of Project Report
Final project report summarising what was delivered, performance against objectives, lessons learned, and recommendations for post-project actions.
End of Project Report
The End of Project Report is the final report produced by the Project Manager, documenting what was achieved, how the project performed, and providing recommendations for follow-on actions and benefits realisation.
Purpose
The End of Project Report:
- Documents project achievements
- Compares actual vs planned performance
- Captures lessons learned
- Confirms handover arrangements
- Sets up benefits tracking
- Formally closes the project
Project Closure Process
flowchart LR
A[Final
Delivery] --> B[Prepare End
Project Report] B --> C[Handover to
Operations] C --> D[Project Board
Approval] D --> E[Release
Resources] E --> F[Close
Project] classDef blue fill:#108BB9,stroke:none,color:#fff class A,B,C,D,E,F blue
Delivery] --> B[Prepare End
Project Report] B --> C[Handover to
Operations] C --> D[Project Board
Approval] D --> E[Release
Resources] E --> F[Close
Project] classDef blue fill:#108BB9,stroke:none,color:#fff class A,B,C,D,E,F blue
Report Contents
Essential Sections
| Section | Purpose |
|---|---|
| Executive summary | Overview of project outcome |
| Project achievements | What was delivered |
| Performance | Comparison to baseline |
| Quality | Quality results |
| Benefits | Expected vs realised |
| Lessons learned | Key learning points |
| Handover | Transfer to operations |
| Recommendations | Follow-on actions |
End of Project Report Template
Report Header
| Field | Content |
|---|---|
| Project | Customer Portal Enhancement |
| Project Manager | John Smith |
| Report Date | 10 June 2026 |
| Sponsor | Sarah Williams |
| Distribution | Project Board, PMO, Operations |
Executive Summary
Project Outcome
| Dimension | Status | Commentary |
|---|---|---|
| Overall | Green | Project successfully delivered |
| Objectives | Green | All objectives achieved |
| Schedule | Amber | 7 days late, within tolerance |
| Budget | Green | £12,000 under budget |
| Quality | Green | All acceptance criteria met |
| Benefits | Green | On track for realisation |
Key Messages
| # | Key Message |
|---|---|
| 1 | Project delivered all planned products and capabilities |
| 2 | Customer portal live and operational since 07 June 2026 |
| 3 | Project completed 7 days late but £12,000 under budget |
| 4 | All acceptance criteria met, customer satisfaction high |
| 5 | Benefits tracking in place, Year 1 benefits on track |
Project Achievements
Objectives vs Outcomes
| Objective | Target | Achieved | Status |
|---|---|---|---|
| Deliver customer portal | Live by 31 May | Live 07 June | Met |
| Enable self-service | 80% transactions | Capability live | Met |
| Improve customer satisfaction | +10 NPS | Baseline set | On Track |
| Reduce call centre volume | -25% | Tracking started | On Track |
| Achieve performance targets | <2 sec load | 1.4 sec average | Met |
Products Delivered
| Product | Description | Status |
|---|---|---|
| Customer Portal | Web application | Delivered |
| Mobile-responsive design | Multi-device access | Delivered |
| Self-service features | Account management, payments | Delivered |
| Integration | Backend systems | Delivered |
| Documentation | User guides, support docs | Delivered |
| Training | Staff and customer training | Delivered |
Scope Delivered vs Planned
| Category | Planned | Delivered | Notes |
|---|---|---|---|
| Core features | 12 | 12 | All delivered |
| Nice-to-have features | 5 | 3 | 2 deferred to Phase 2 |
| Integrations | 4 | 4 | All delivered |
| Support documentation | 6 docs | 8 docs | Exceeded |
Performance Summary
Schedule Performance
| Stage | Planned Duration | Actual Duration | Variance |
|---|---|---|---|
| Stage 1 - Design | 4 weeks | 4 weeks | 0 |
| Stage 2 - Development | 11 weeks | 11.5 weeks | +3 days |
| Stage 3 - Testing | 5 weeks | 5.5 weeks | +2 days |
| Stage 4 - Deployment | 4 weeks | 4.5 weeks | +2 days |
| Total | 24 weeks | 25 weeks | +7 days |
Milestone Summary
| Milestone | Planned | Actual | Variance |
|---|---|---|---|
| Project Start | 01 Jan | 01 Jan | 0 |
| Design Complete | 28 Jan | 28 Jan | 0 |
| Development Complete | 31 Mar | 03 Apr | +3 days |
| UAT Complete | 05 May | 10 May | +5 days |
| Go-Live | 31 May | 07 Jun | +7 days |
Cost Performance
| Category | Budget | Actual | Variance |
|---|---|---|---|
| Labour - Internal | £95,000 | £98,000 | +£3,000 |
| Labour - External | £55,000 | £40,000 | -£15,000 |
| Infrastructure | £25,000 | £25,000 | £0 |
| Software/Licences | £15,000 | £15,000 | £0 |
| Training | £10,000 | £10,000 | £0 |
| Contingency | £20,000 | £0 | -£20,000 |
| Total | £220,000 | £188,000 | -£32,000 |
Budget Analysis
| Metric | Value |
|---|---|
| Original budget | £200,000 |
| Approved changes | +£20,000 |
| Final budget | £220,000 |
| Actual spend | £188,000 |
| Underspend | £32,000 (14.5%) |
Quality Summary
Quality Performance
| Metric | Target | Actual | Status |
|---|---|---|---|
| Defects at go-live | <20 | 8 | Met |
| Critical defects | 0 | 0 | Met |
| Test coverage | >80% | 87% | Met |
| UAT pass rate | 100% | 100% | Met |
| Security vulnerabilities | 0 critical | 0 | Met |
Acceptance Criteria
| Criterion | Met |
|---|---|
| All functional requirements delivered | Yes |
| Performance targets achieved | Yes |
| Security review passed | Yes |
| Accessibility standards met | Yes |
| User acceptance sign-off | Yes |
| Operations acceptance | Yes |
Benefits Summary
Benefits Realisation Status
| Benefit | Target | Current | Measurement |
|---|---|---|---|
| Self-service adoption | 60% by Month 6 | 15% (Month 1) | Portal analytics |
| Call volume reduction | -25% by Month 12 | -5% (Month 1) | Call centre data |
| Customer satisfaction | +10 NPS | Baseline set | Survey |
| Cost savings | £150k/year | Tracking | Finance reports |
Benefits Tracking Arrangements
| Benefit | Owner | Measurement | Frequency |
|---|---|---|---|
| Self-service adoption | Digital Director | Portal analytics | Monthly |
| Call volume reduction | Operations Director | Call centre reports | Monthly |
| Customer satisfaction | Customer Experience | NPS survey | Quarterly |
| Cost savings | Finance Director | Cost tracking | Quarterly |
Benefits Review Schedule
| Review | Date | Purpose |
|---|---|---|
| Month 3 review | Sep 2026 | Early adoption check |
| Month 6 review | Dec 2026 | Milestone review |
| Month 12 review | Jun 2027 | Full benefits assessment |
Issues and Changes
Significant Issues
| Issue | Impact | Resolution |
|---|---|---|
| Third-party API delays | 3-day delay | Worked with vendor |
| UAT resource availability | 2-day delay | Brought in additional staff |
| Production environment setup | 2-day delay | Escalated and resolved |
Changes Implemented
| Change | Impact | Benefit |
|---|---|---|
| Additional SSO provider | +2 days, +£2,000 | Broader customer access |
| Enhanced error handling | +1 day | Better user experience |
| Extended reporting | +£5,000 | Improved management info |
Deferred Items
| Item | Reason | Disposition |
|---|---|---|
| Dark mode | Out of scope | Phase 2 backlog |
| Advanced reporting | Time constraints | Phase 2 backlog |
| Mobile app | Scope limitation | Separate project |
Lessons Learned
Top Lessons
| # | Lesson | Recommendation |
|---|---|---|
| 1 | Early QA involvement reduced defects significantly | Build QA into project from start |
| 2 | Third-party integration complexity was underestimated | Add contingency for external dependencies |
| 3 | Regular demos kept stakeholders engaged | Weekly demos for all future projects |
| 4 | Cross-training reduced key person risk | Mandate cross-training on all projects |
| 5 | Documentation started too late | Begin documentation in parallel with development |
What Went Well
| Area | Success Factor |
|---|---|
| Team collaboration | Daily stand-ups, open communication |
| Stakeholder engagement | Regular demos, responsive to feedback |
| Quality | Early testing, automated checks |
| Risk management | Proactive identification and mitigation |
What Could Be Improved
| Area | Improvement |
|---|---|
| Third-party coordination | Earlier engagement, more contingency |
| Documentation timing | Start earlier, parallel with development |
| UAT planning | Secure resources earlier |
| Training materials | Allow more preparation time |
Handover Summary
Operational Handover
| Item | Handed To | Date | Status |
|---|---|---|---|
| Application | IT Operations | 07 Jun | Complete |
| Documentation | IT Service Desk | 05 Jun | Complete |
| Support procedures | Service Management | 05 Jun | Complete |
| Monitoring | IT Operations | 07 Jun | Complete |
| Training | Learning & Development | 01 Jun | Complete |
Support Arrangements
| Aspect | Arrangement |
|---|---|
| Hypercare period | 4 weeks (to 05 July 2026) |
| Hypercare support | Development team on standby |
| BAU support | IT Service Desk (L1), Application Support (L2) |
| Escalation | To IT Operations Manager |
Outstanding Items
| Item | Owner | Due Date |
|---|---|---|
| Final documentation review | Operations | 15 Jun |
| Knowledge transfer sessions | Development | 14 Jun |
| Post-implementation review | PMO | 10 Jul |
Recommendations
Follow-On Actions
| Action | Owner | Priority | Timeframe |
|---|---|---|---|
| Complete hypercare period | Development Lead | High | 4 weeks |
| Conduct post-implementation review | PMO | Medium | July 2026 |
| Plan Phase 2 features | Product Owner | Medium | Q3 2026 |
| Review benefits at Month 3 | Sponsor | High | Sep 2026 |
Recommendations for Future Projects
| Recommendation | Rationale |
|---|---|
| Allocate integration contingency | Complexity often exceeds estimates |
| Secure UAT resources early | Availability is often constrained |
| Start documentation in parallel | Reduces end-of-project rush |
| Mandate cross-training | Reduces key-person dependency |
Project Closure
Closure Checklist
| Item | Status |
|---|---|
| All products delivered and accepted | ☑ |
| All documentation handed over | ☑ |
| Support arrangements in place | ☑ |
| Benefits tracking established | ☑ |
| Lessons learned captured | ☑ |
| Project files archived | ☐ |
| Resources released | ☐ |
| Project accounts closed | ☐ |
| Closure notification issued | ☐ |
Resource Release
| Resource | Current Role | Release Date | Destination |
|---|---|---|---|
| John Smith | PM | 14 Jun | New project |
| Jane Doe | Dev Lead | 05 Jul | Operations |
| Bob Wilson | Developer | 14 Jun | Resource pool |
| Dave Jones | QA Lead | 21 Jun | New project |
Final Sign-off
Project Board Confirmation
| Confirmation | Agreed |
|---|---|
| Project deliverables accepted | ☐ |
| Performance acknowledged | ☐ |
| Handover complete | ☐ |
| Benefits tracking in place | ☐ |
| Lessons captured | ☐ |
| Project authorised to close | ☐ |
Signatures
| Role | Name | Signature | Date |
|---|---|---|---|
| Project Sponsor | |||
| Senior User | |||
| Senior Supplier | |||
| Project Manager |
End of Project Report Checklist
Preparation
- All products signed off?
- Performance data compiled?
- Quality results documented?
- Benefits baseline set?
- Lessons captured?
- Handover complete?
- Outstanding items listed?
Review
- Report reviewed by sponsor?
- PMO review complete?
- Board meeting scheduled?
Closure
- Board approval received?
- Files archived?
- Resources released?
- Accounts closed?
- Closure notification sent?
Related Resources
- Project Closure Report - Closure documentation
- Benefits Review - Benefits assessment
- Lessons Learned - Learning capture
- Handover Document - Operational handover
- Post Implementation Review - Post-project review
Last updated: 13 January 2026