Stage Plan
Detailed planning for a project stage, providing the baseline for day-to-day control and progress monitoring.
Stage Plan
A Stage Plan provides detailed planning for a management stage, forming the baseline against which the Project Manager monitors and controls day-to-day progress.
Purpose
The Stage Plan:
- Details how the stage will be delivered
- Provides the control baseline
- Enables day-to-day monitoring
- Identifies resources required
- Sets tolerances for the stage
- Supports progress reporting
Planning Hierarchy
flowchart TD
A[Project Plan] --> B[Stage 1 Plan]
A --> C[Stage 2 Plan]
A --> D[Stage 3 Plan]
C --> E[Work Package 1]
C --> F[Work Package 2]
C --> G[Work Package 3]
classDef blue fill:#108BB9,stroke:none,color:#fff
class A,B,C,D,E,F,G blue
| Plan Level | Detail | Owned By |
|---|---|---|
| Project Plan | High-level, entire project | Project Board |
| Stage Plan | Detailed, single stage | Project Manager |
| Work Package | Specific work delegation | Team Manager |
Stage Plan Contents
Essential Elements
| Section | Content |
|---|---|
| Stage overview | Objectives, scope, approach |
| Products | What will be delivered |
| Activities | Work to be performed |
| Schedule | Timeline and milestones |
| Resources | People, budget, equipment |
| Dependencies | Internal and external |
| Risks | Stage-specific risks |
| Controls | Monitoring and reporting |
| Tolerances | Permitted variance |
Stage Plan Template
Stage Overview
| Field | Content |
|---|---|
| Project | Customer Portal Enhancement |
| Stage | Stage 2 - Development |
| Stage Manager | John Smith (PM) |
| Stage Start | 15 January 2026 |
| Stage End | 31 March 2026 |
| Version | 1.0 |
| Status | Approved |
Stage Objectives
| Objective | Success Criteria |
|---|---|
| Deliver core portal functionality | Login, Dashboard, Profile complete |
| Complete integration testing | All integration tests pass |
| Achieve performance targets | <2 second page load times |
| Prepare for UAT | Test environment ready, test cases prepared |
Stage Scope
| In Scope | Out of Scope |
|---|---|
| Login functionality | Mobile app |
| Dashboard | Admin portal |
| User profile | Reporting module |
| Integration testing | Performance testing |
| Documentation | Training delivery |
Products
Product List
| Product ID | Product | Description | Target Date |
|---|---|---|---|
| PD-101 | Login Screen | Customer authentication | 14 Feb |
| PD-102 | Dashboard | Main landing page | 28 Feb |
| PD-103 | User Profile | Account management | 14 Mar |
| PD-104 | Integration Tests | Automated test suite | 21 Mar |
| PD-105 | Technical Docs | System documentation | 28 Mar |
Product Flow
flowchart LR
A[Requirements
Complete] --> B[Login
Screen] A --> C[Dashboard] A --> D[User
Profile] B --> E[Integration
Testing] C --> E D --> E E --> F[Technical
Docs] F --> G[Stage
Complete] classDef blue fill:#108BB9,stroke:none,color:#fff class A,B,C,D,E,F,G blue
Complete] --> B[Login
Screen] A --> C[Dashboard] A --> D[User
Profile] B --> E[Integration
Testing] C --> E D --> E E --> F[Technical
Docs] F --> G[Stage
Complete] classDef blue fill:#108BB9,stroke:none,color:#fff class A,B,C,D,E,F,G blue
Activities
Activity List
| ID | Activity | Duration | Predecessors | Resources |
|---|---|---|---|---|
| A1 | Setup development environment | 5 days | - | Dev Lead |
| A2 | Develop Login Screen | 15 days | A1 | 2 Developers |
| A3 | Develop Dashboard | 20 days | A1 | 2 Developers |
| A4 | Develop User Profile | 15 days | A2 | 2 Developers |
| A5 | API Integration | 10 days | A2, A3, A4 | Dev Lead |
| A6 | Integration Testing | 10 days | A5 | QA Team |
| A7 | Documentation | 5 days | A5 | BA |
| A8 | Stage Review | 2 days | A6, A7 | PM |
Activity Network
flowchart LR
A1[A1: Setup
5 days] --> A2[A2: Login
15 days] A1 --> A3[A3: Dashboard
20 days] A2 --> A4[A4: Profile
15 days] A2 --> A5[A5: Integration
10 days] A3 --> A5 A4 --> A5 A5 --> A6[A6: Testing
10 days] A5 --> A7[A7: Docs
5 days] A6 --> A8[A8: Review
2 days] A7 --> A8 classDef blue fill:#108BB9,stroke:none,color:#fff class A1,A2,A3,A4,A5,A6,A7,A8 blue
5 days] --> A2[A2: Login
15 days] A1 --> A3[A3: Dashboard
20 days] A2 --> A4[A4: Profile
15 days] A2 --> A5[A5: Integration
10 days] A3 --> A5 A4 --> A5 A5 --> A6[A6: Testing
10 days] A5 --> A7[A7: Docs
5 days] A6 --> A8[A8: Review
2 days] A7 --> A8 classDef blue fill:#108BB9,stroke:none,color:#fff class A1,A2,A3,A4,A5,A6,A7,A8 blue
Schedule
Milestone Schedule
| Milestone | Target Date | Status |
|---|---|---|
| Stage Start | 15 Jan 2026 | Complete |
| Dev Environment Ready | 20 Jan 2026 | On Track |
| Login Screen Complete | 14 Feb 2026 | On Track |
| Dashboard Complete | 28 Feb 2026 | On Track |
| Profile Complete | 14 Mar 2026 | On Track |
| Integration Complete | 21 Mar 2026 | On Track |
| Stage End | 31 Mar 2026 | On Track |
Gantt Chart Summary
Task Jan Feb Mar
Setup ████
Login Development ████████████
Dashboard Development ████████████████████
Profile Development ████████████
API Integration ████████
Integration Testing ████████
Documentation ████
Stage Review ██
Resources
Resource Plan
| Resource | Role | Allocation | Period |
|---|---|---|---|
| John Smith | Project Manager | 50% | Full stage |
| Jane Doe | Dev Lead | 100% | Full stage |
| Bob Wilson | Developer | 100% | Weeks 1-10 |
| Carol Brown | Developer | 100% | Weeks 1-10 |
| Dave Jones | QA Lead | 50% | Weeks 8-11 |
| Eve Taylor | BA | 50% | Weeks 9-11 |
Resource Loading
| Week | PM | Dev Lead | Dev 1 | Dev 2 | QA | BA |
|---|---|---|---|---|---|---|
| 1 | 50% | 100% | 100% | 100% | - | - |
| 2-4 | 50% | 100% | 100% | 100% | - | - |
| 5-7 | 50% | 100% | 100% | 100% | - | - |
| 8-9 | 50% | 100% | 100% | 100% | 50% | - |
| 10 | 50% | 100% | 50% | 50% | 100% | 50% |
| 11 | 50% | 100% | - | - | 100% | 100% |
Budget
Stage Budget
| Category | Budget | Forecast | Variance |
|---|---|---|---|
| Labour - Internal | £45,000 | £45,000 | £0 |
| Labour - External | £20,000 | £18,000 | £2,000 |
| Infrastructure | £5,000 | £5,000 | £0 |
| Tools/Licences | £3,000 | £3,500 | -£500 |
| Contingency | £7,000 | £0 | £7,000 |
| Total | £80,000 | £71,500 | £8,500 |
Dependencies
Internal Dependencies
| Dependency | Source | Required By | Status |
|---|---|---|---|
| API specifications | Stage 1 | Week 1 | Complete |
| Test data | QA Team | Week 8 | On Track |
| Security review | Security Team | Week 10 | On Track |
External Dependencies
| Dependency | Provider | Required By | Status |
|---|---|---|---|
| Cloud environment | AWS | Week 1 | Complete |
| SSL certificates | Certificate provider | Week 9 | On Track |
| Payment gateway API | Third party | Week 8 | At Risk |
Risks
Stage-Specific Risks
| ID | Risk | Probability | Impact | Response |
|---|---|---|---|---|
| R1 | Key developer unavailable | Medium | High | Cross-train, contract backup |
| R2 | API integration issues | Medium | Medium | Early spike, vendor contact |
| R3 | Performance targets not met | Low | High | Early performance testing |
| R4 | Scope creep | Medium | Medium | Change control, scope freeze |
Controls
Progress Monitoring
| Control | Frequency | Audience |
|---|---|---|
| Daily stand-up | Daily | Delivery team |
| Checkpoint report | Weekly | PM |
| Highlight report | Fortnightly | Project Board |
| Milestone review | At milestones | PM, Team Leads |
Quality Controls
| Control | When Applied |
|---|---|
| Code review | Before merge |
| Unit testing | During development |
| Integration testing | After component completion |
| Quality gate | Before stage end |
Tolerances
Stage Tolerances
| Dimension | Tolerance | Escalation |
|---|---|---|
| Time | +10 days / -5 days | Project Board |
| Cost | +£8,000 / -£8,000 (10%) | Project Board |
| Scope | No deviation | Project Board |
| Quality | As per quality criteria | PM |
| Risk | New high-impact risk | Project Board |
Creating a Stage Plan
Process
flowchart LR
A[Review
Project Plan] --> B[Define
Products] B --> C[Identify
Activities] C --> D[Estimate &
Schedule] D --> E[Assign
Resources] E --> F[Analyse
Risks] F --> G[Set
Controls] G --> H[Seek
Approval] classDef blue fill:#108BB9,stroke:none,color:#fff class A,B,C,D,E,F,G,H blue
Project Plan] --> B[Define
Products] B --> C[Identify
Activities] C --> D[Estimate &
Schedule] D --> E[Assign
Resources] E --> F[Analyse
Risks] F --> G[Set
Controls] G --> H[Seek
Approval] classDef blue fill:#108BB9,stroke:none,color:#fff class A,B,C,D,E,F,G,H blue
Planning Steps
| Step | Activities |
|---|---|
| 1. Understand context | Review project plan, previous stage |
| 2. Define products | List products, create descriptions |
| 3. Identify activities | Break down work, sequence activities |
| 4. Estimate | Effort, duration, cost |
| 5. Schedule | Create timeline, identify critical path |
| 6. Resource | Assign resources, resolve conflicts |
| 7. Risk | Identify and plan for risks |
| 8. Controls | Set tolerances, reporting |
| 9. Document | Compile stage plan |
| 10. Approve | Present to Project Board |
Stage Plan Approval
Approval Criteria
| Criterion | Evidence |
|---|---|
| Products clearly defined | Product descriptions complete |
| Schedule realistic | Resource availability confirmed |
| Budget adequate | Cost estimates validated |
| Risks identified | Risk register updated |
| Dependencies managed | Owners confirmed |
| Controls appropriate | Reporting schedule agreed |
Sign-off
| Role | Name | Signature | Date |
|---|---|---|---|
| Project Manager | |||
| Project Sponsor | |||
| Senior User | |||
| Senior Supplier |
Stage Plan Checklist
Before Approval
- Objectives clear and measurable?
- Products fully defined?
- Activities comprehensive?
- Schedule realistic?
- Resources available and assigned?
- Budget adequate?
- Dependencies identified?
- Risks assessed?
- Controls defined?
- Tolerances set?
During Stage
- Progress tracked against plan?
- Issues and changes managed?
- Risks monitored?
- Resources managed?
- Quality maintained?
- Reports produced?
Related Resources
- Project Planning - Planning techniques
- Work Package - Work delegation
- End of Stage Report - Stage closure
- Project Reporting - Progress reporting
- Risk Register - Risk management