End of Stage Report
Formal report summarising stage performance to support the Project Board's decision to proceed, enabling informed stage gate decisions.
End of Stage Report
The End of Stage Report provides the Project Board with information needed to decide whether to authorise the next stage, covering what was achieved, how the stage performed, and the forecast for the remainder of the project.
Purpose
The End of Stage Report:
- Summarises stage achievements
- Reports performance against plan
- Identifies issues and lessons
- Forecasts project completion
- Supports stage gate decisions
- Updates the business case
Stage Gate Process
flowchart LR
A[Stage
Complete] --> B[Prepare End
Stage Report]
B --> C[Present to
Project Board]
C --> D{Decision}
D -->|Approve| E[Start
Next Stage]
D -->|Exception| F[Exception
Plan]
D -->|Stop| G[Premature
Close]
classDef blue fill:#108BB9,stroke:none,color:#fff
class A,B,C,D,E,F,G blue
Report Contents
Essential Sections
| Section |
Purpose |
| Executive summary |
Key messages for quick review |
| Stage achievements |
What was delivered |
| Performance |
Time, cost, quality, scope |
| Issues and changes |
Problems and resolutions |
| Lessons learned |
What to improve |
| Forecast |
Updated project outlook |
| Recommendation |
Proceed, modify, or stop |
End of Stage Report Template
| Field |
Content |
| Project |
Customer Portal Enhancement |
| Stage |
Stage 2 - Development |
| Report Date |
31 March 2026 |
| Project Manager |
John Smith |
| Distribution |
Project Board, PMO |
Executive Summary
Stage Status
| Dimension |
Status |
Commentary |
| Overall |
Amber |
Stage complete with minor delays |
| Schedule |
Amber |
5 days late, within tolerance |
| Budget |
Green |
£3,000 under budget |
| Quality |
Green |
All quality criteria met |
| Scope |
Green |
All products delivered |
| Risk |
Amber |
One high risk materialised |
Key Messages
| # |
Key Message |
| 1 |
All planned products delivered with quality criteria met |
| 2 |
Stage completed 5 days late due to API integration issues |
| 3 |
Budget underspent by £3,000 (4%) |
| 4 |
Business case remains valid with minor schedule adjustment |
| 5 |
Recommend approval to proceed to Stage 3 |
Stage Achievements
Products Delivered
| Product |
Planned Date |
Actual Date |
Quality |
| Login Screen |
14 Feb |
14 Feb |
Approved |
| Dashboard |
28 Feb |
05 Mar |
Approved |
| User Profile |
14 Mar |
19 Mar |
Approved |
| Integration Tests |
21 Mar |
28 Mar |
Approved |
| Technical Docs |
28 Mar |
31 Mar |
Approved |
Milestones
| Milestone |
Planned |
Actual |
Variance |
| Stage Start |
15 Jan |
15 Jan |
0 days |
| Dev Environment Ready |
20 Jan |
20 Jan |
0 days |
| Login Complete |
14 Feb |
14 Feb |
0 days |
| Dashboard Complete |
28 Feb |
05 Mar |
+5 days |
| Integration Complete |
21 Mar |
28 Mar |
+7 days |
| Stage End |
28 Mar |
31 Mar |
+3 days |
Key Accomplishments
| Accomplishment |
Impact |
| Delivered full portal functionality |
Enables user acceptance testing |
| Achieved performance targets |
<1.5 second page loads |
| Completed security review |
No vulnerabilities found |
| Built comprehensive test suite |
85% code coverage |
| Metric |
Planned |
Actual |
Variance |
| Duration |
11 weeks |
11.5 weeks |
+0.5 weeks |
| Effort |
400 person-days |
410 person-days |
+10 days |
| Milestones on time |
6 |
4 |
-2 |
Schedule Analysis: API integration complexity exceeded estimates. Recovery achieved through parallel working and weekend work. Overall delay of 5 days within tolerance (+10 days).
| Category |
Budget |
Actual |
Variance |
| Labour - Internal |
£45,000 |
£46,000 |
+£1,000 |
| Labour - External |
£20,000 |
£16,000 |
-£4,000 |
| Infrastructure |
£5,000 |
£5,000 |
£0 |
| Tools/Licences |
£3,000 |
£3,000 |
£0 |
| Contingency used |
£7,000 |
£0 |
-£7,000 |
| Total |
£80,000 |
£70,000 |
-£10,000 |
Cost Analysis: Stage completed £10,000 (12.5%) under budget. External contractor days reduced through internal upskilling. Contingency not required.
| Metric |
Target |
Actual |
Status |
| Code review completion |
100% |
100% |
Met |
| Unit test coverage |
>80% |
85% |
Met |
| Integration tests passing |
100% |
100% |
Met |
| Defects at handover |
<10 |
3 |
Met |
| Performance target |
<2 sec |
1.4 sec |
Met |
Issues and Changes
Issues Resolved
| Issue |
Impact |
Resolution |
| API rate limiting |
Delayed integration |
Implemented caching |
| Database performance |
Slow queries |
Query optimisation |
| SSL certificate delay |
Blocked testing |
Used temporary certs |
Outstanding Issues
| Issue |
Impact |
Mitigation |
| Mobile responsiveness |
Minor display issues |
Fix in Stage 3 |
| Edge browser quirk |
Affects 2% of users |
Workaround documented |
Changes Approved
| RFC |
Description |
Impact |
| RFC-003 |
Additional SSO provider |
+2 days, +£500 |
| RFC-005 |
Enhanced error handling |
+1 day, no cost |
Changes Deferred
| RFC |
Description |
Reason |
| RFC-004 |
Dark mode |
Out of scope, future phase |
| RFC-006 |
API versioning |
Complexity, defer to Stage 3 |
Risk Update
Risks Materialised
| Risk |
Impact |
Response |
| R2: API integration issues |
5-day delay |
Extended testing, vendor support |
Current High Risks
| Risk |
Probability |
Impact |
Mitigation |
| UAT resource availability |
Medium |
High |
Early booking confirmed |
| Production environment |
Low |
High |
Parallel preparation |
Lessons Learned
What Went Well
| Lesson |
Application |
| Daily stand-ups improved coordination |
Continue in Stage 3 |
| Early QA involvement reduced defects |
Maintain approach |
| Cross-training reduced key-person risk |
Expand practice |
What Could Be Improved
| Lesson |
Action |
| Third-party API complexity underestimated |
Add buffer for integration |
| Documentation started late |
Begin documentation earlier |
| Stakeholder demos could be more frequent |
Weekly demo sessions |
Project Forecast
Updated Project Timeline
| Stage |
Original End |
Forecast End |
Variance |
| Stage 1 - Design |
14 Jan |
14 Jan |
0 |
| Stage 2 - Development |
28 Mar |
31 Mar |
+3 days |
| Stage 3 - Testing |
30 Apr |
05 May |
+5 days |
| Stage 4 - Deployment |
31 May |
05 Jun |
+5 days |
Updated Project Budget
| Category |
Original |
Forecast |
Variance |
| Stage 1 |
£30,000 |
£29,000 |
-£1,000 |
| Stage 2 |
£80,000 |
£70,000 |
-£10,000 |
| Stage 3 |
£50,000 |
£52,000 |
+£2,000 |
| Stage 4 |
£40,000 |
£40,000 |
£0 |
| Total |
£200,000 |
£191,000 |
-£9,000 |
Business Case Update
| Metric |
Original |
Revised |
Status |
| Total cost |
£200,000 |
£191,000 |
Better |
| Completion date |
31 May |
05 Jun |
Acceptable |
| Year 1 benefits |
£150,000 |
£145,000 |
Slight reduction |
| NPV |
£320,000 |
£315,000 |
Still positive |
| ROI |
160% |
165% |
Improved |
Next Stage Plan Summary
Stage 3 Overview
| Element |
Detail |
| Stage name |
Stage 3 - Testing and UAT |
| Duration |
5 weeks |
| Budget |
£52,000 |
| Key products |
UAT completion, bug fixes, performance tuning |
| Key milestone |
UAT sign-off by 05 May |
Stage 3 Resources
| Resource |
Allocation |
Period |
| Project Manager |
50% |
Full stage |
| QA Lead |
100% |
Full stage |
| Testers (2) |
100% |
Weeks 1-4 |
| Developers (2) |
50% |
Full stage |
| Business SMEs |
50% |
Weeks 2-4 |
Recommendation
Options
| Option |
Description |
Recommendation |
| 1. Approve Stage 3 |
Proceed as planned |
Recommended |
| 2. Approve with conditions |
Proceed with specific changes |
Not required |
| 3. Request exception plan |
Major replanning needed |
Not applicable |
| 4. Stop project |
Terminate project |
Not recommended |
Recommendation
Approve Stage 3 as presented. The project remains on track to deliver planned benefits with only minor schedule variance. Budget performance is positive, and all quality criteria have been met.
Approval
Project Board Decision
| Decision |
Selected |
| Approve Stage 3 |
☐ |
| Approve with conditions |
☐ |
| Request exception plan |
☐ |
| Stop project |
☐ |
Conditions (if applicable)
Sign-off
| Role |
Name |
Signature |
Date |
| Project Sponsor |
|
|
|
| Senior User |
|
|
|
| Senior Supplier |
|
|
|
End of Stage Report Checklist
Preparation
Review
Post-Meeting
Last updated: 13 January 2026